Lysimeter Station Wagna
Installing a lysimeter in spring 2006
 
 
 
 
Step 3
Figure 3: Installing suction cups

 

• The lysimeter cylinder filled with soil is then lifted from the hole, turned round and put on the ground near the pit with the upside down.

• The bottom plate and several centimetesr of the natural soil are removed. 7 suction cups (of different sizes) for collecting seepage water are installed, see figure 3. Soil is replaced by different sizes of filter sand and gravel from top to bottom.

• The bottom of the lysimeter is covered with a fleece and a stainless steel bottom plate is mounted to the container. At the same time, soil samples of all horizons are taken to be analyzed for different parameters.

 
 
show previous step show next step
   
 
 
 
 
 
 
last update: July 25, 2006